1.活动房雨天施工时,宜搭设临时防护棚,雨水不得飘落在炽热的焊缝上.如焊接部位比较潮湿,必须用干布擦净并在焊接前用氧炔焰烤干,保持接缝干燥,没有残留水分。
1. During the construction of activity room in rainy days, temporary protective shed should be set up, and the rain should not fall on the hot welding seam. If the welding part is wet, it must be cleaned with dry cloth and dried with oxyacetylene flame before welding, so as to keep the joints dry without residual moisture.
2.活动房吊装时,构件上如有积水,安装前应干净,但不得损涂层,高强螺栓接头安装时,构件摩擦面应干净,不能有水珠,更不能雨淋和接触泥土及油污等脏物。
2. During the hoisting of the mobile house, if there is water on the component, it should be cleaned before installation, but the coating should not be damaged. When the high-strength bolt joint is installed, the friction surface of the component should be clean, without water droplets, rain, soil, oil and other dirt.
3.雨天天气构件不能进行涂刷工作。
3. The component cannot be painted in rainy days.
4.雨天及五级以上大风不能进行屋面保温的施工。
4. Roof insulation construction can not be carried out in rainy days and strong wind above level 5.
5.雨天由于空气比较潮湿,焊条储存应防潮并进行烘烤,同一焊条重复烘烤次数不宜超过两次,并由管理人员及时做好烤记录。
5. In rainy days, because the air is humid, the welding rod should be stored in moisture-proof and baked. The same welding rod should not be baked more than twice, and the management personnel should make baking records in time.
6.如遇上大风天气,柱、主梁、支撑等大构件应立即进行校正,位置校正正确后立即进行固定,以防止发生单侧失稳.当天安装的构件,应形成空间稳定体系。
6. In case of gale weather, the column, main beam, support and other large components shall be corrected immediately. After the correct position correction, they shall be permanently fixed immediately to prevent unilateral instability. The components installed on that day shall form a space stable system.